26.07.2024
05.07.2024
07.06.2024
Cleaning of the apartments continues. Terminal devices are being installed in the buildings of Blocks A and B. Door blocks are being installed. In the five-star hotel, finishing of the public spaces, restaurants and spas continues. Installation of decorative lighting and decorative elements in the spa and pool areas is underway. In the interior area, paving stones are being laid, plants are being planted, and pools are being commissioned.
17.05.2024
In the residences, finishing works are being performed, parquet and marble are being laid. The installation of interior doors is being completed. At the MANTERA Supreme Hotel, finishing works are being performed in the restaurant on the 8th floor, the rooms are being furnished, finishing works are also being performed in the public spaces. Inside the complex territory, small architectural pieces are being installed and checkpoints have been built. The laying of paving stones and the construction of bungalows continues. Landscaping work is underway.
12.04.2024
Finishing work is being carried out, floor coverings are being laid, marble and doors are being installed in the public space of the residences of MANTERA Seaview residence. The work on installing the lamellas has been completed. In the 5-star hotel, the restaurant premises on the 8th floor are being decorated, interior elements of the public spaces are being installed, and rooms are being furnished. Outside of the elite complex, landscaping, the installation of small architectural forms, the installation of bungalows, and the installation of bridges near the Slow River pool continues.
26.01.2024
In MANTERA Seaview Residence the walls in the bathrooms are being covered with marble, finishing works are in progress, interior doors are being installed. The 5* hotel continues furniture assembly, finishing of rooms, common areas, elevator halls. Interior finishing is being completed in the conference center. On the territory of the complex travertine and paving stones are being laid, bungalows with mini-bars are being installed, landscaping is underway.
26.12.2023
Finishing work, laying of parquet, and installation of doors continues in the residences of the MATERA Seaview residence. The rooms, the reception area, the public areas, the elevator halls are being finished, furniture is being assembled in the hotel. In the convention centre, finishing work is being carried out and doors are being installed. In the internal area, paving stones are being laid, street lighting masts are being installed, landscape lighting is being installed, and small architectural forms are being installed.
12.12.2023
Residence buildings are being finished and the doors are being installed. Overall, they are more than 85% ready. The five-star hotel is finishing up its rooms and installing internal communications. The installation of the engineering systems is being completed. Overall, the hotel is more than 90% ready. The finishing touches are being put in the convention centre. The facility readiness exceeds 80%. At the complex, the roads and the sidewalks are being installed, and the installation of the on-site networks is being completed.
28.11.2023
Deluxe-class MANTERA Seaview residence complex construction progress in Sochi. Overall, the residences are 85% ready, the finishing work is underway and the doors are being installed. The 5* hotel is 89% complete, the utilities are 91% complete. The final finishing of the hotel rooms continues. The convention centre is 81% complete, the finishing work is underway. The landscaping of the territory is being completed and the roads and the sidewalks are being laid. The installation of the on-site networks is being completed and preparations for commissioning are underway.
14.11.2023
The residences are undergoing final finishing, the doors and energy meters are being installed. As for the hotel, finishing work and furnishing of the rooms continues. The convention centre is also at the finishing stage. Builders are installing roads and sidewalks inside MATERA Seaview residence. The installation of on-site networks is also being completed and they are being prepared for commissioning.
07.11.2023
The MATERA Seaview residence has ventilation and air conditioning systems installed. The installation of equipment and preparation for commissioning work is underway. Supply and exhaust ventilation with heat recovery will be ensuring a comfortable temperature regime in the buildings all year round. The energy-efficient climate control system adapts to external conditions and internal consumption. This will ensure high air quality in the residences, as well as heating, cooling, depending on the time of year, and purification. Supply and exhaust ventilation will create continuous air exchange: the entry of air purified from dust and dirt into the premises and the removal of exhaust air. The installed ventilation equipment is fully automated.
27.10.2023
The MATERA Seaview residence project is nearing completion. The overall the residences are 84% ready. The engineering systems are 90% ready. The installation of the walls and the partitions is being completed. The five-star hotel is 82% ready overall. The utility networks are 81% installed. The convention center is 79% complete, 69% of the façade work has been completed, and the installation of the partitions is being completed. The on-site networks are 89.5% ready.
13.10.2023
Overall, the residences are 83% ready. The walls and the partitions are 97% complete. The façade is 67% ready. The internal finishing is 59% complete. The engineering systems are 87% complete. The 5* hotel is 82% ready, the convention center is 78% complete, the pools are 85% complete. The landscaping of the territory of the complex is 42% complete.
15.09.2023
Overall, the residences are 82% ready. The walls and the partitions are 96% complete. The façade is 66% ready, the internal finishing is 57% complete, the engineering systems are 87% complete. The 5* hotel is 78% ready. The convention center is 74% complete. The pools are 85% complete. The landscaping of the territory of the complex is 38% complete. There is very little time left before the elite complex opens its doors to its residents.
04.08.2023
The total readiness of the residences is 81%. Walls and partitions are 93% complete. The façade is 64% ready, interior finishing - 55%, engineering systems - 87%. The five-star hotel is 77% ready. The construction of the congress center continues. The building is 72% ready. The swimming pools are 80% complete. The landscaping of the complex territory is 38% complete. Every day the complex is being transformed, getting closer and closer to the final appearance.
26.07.2023
The total readiness of the residences is 81%. Walls and partitions are 92% complete. Facade - 64%, interior finishing - 55%, engineering systems - 87%. The five-star hotel is 77% complete. The congress center building is 71% complete. Readiness of swimming pools - 78%. Landscaping of the complex territory - 31%.
02.06.2023
Overall, the residences are 80,5% ready. The walls and the partitions are 89.6% complete. The façade is 62,2% ready, the internal finishing is 53% complete, the engineering systems are 86.5% complete. The five-star hotel is 74,3% ready. The construction of the convention center continues. The building is 69,7% ready. The pools are 74,6% complete. The landscaping of the territory of the complex is 29,5% complete.
12.05.2023
Overall, the residences are 80,5% ready. The walls and the partitions are 89.6% complete. The façade is 60% ready, the internal finishing is 53% complete, the engineering systems are 86.5% complete. The five-star hotel is 74% ready. The construction of the convention center continues. The building is 68.6% ready. The pools are 69,4% complete. The landscaping of the territory of the complex is 27,4% complete.
05.05.2023
Overall, the residences are 80% ready. The walls and the partitions are 89.6% complete. The façade is 60% ready, the internal finishing is 53% complete, the engineering systems are 86.5% complete. The five-star hotel is 73.8% ready. The construction of the convention center continues. The building is 68.6% ready. The pools are 67% complete. The landscaping of the territory of the complex is 26.5% complete
14.04.2023
Overall, the residences are 81% ready. The walls and the partitions are 89,5% complete. The internal residence finishing is 53% complete, the engineering systems are 86,5% complete. The five-star hotel is 73% ready. The convention center is 68% ready. The pools are 62% complete. The landscaping of the territory of the complex continues.
We will pick a residence for you and prepare a calculation of its profit potential. please leave your contact details for a personal offer.
Soon the start of sales of a new pool of residences.
Leave a request, we will add you to the waiting list.
SOON THE START OF SALES OF A NEW POOL OF RESIDENCES.
LEAVE A REQUEST, WE WILL ADD YOU TO THE WAITING LIST
SOLD OUT*
We are pleased to put you on the waiting list for another FIVE project.
Soon the start of sales of a new pool of residences.
Leave a request, we will add you to the waiting list.
Welcome toMantera Seaview residence! Be the first to book the best option when the sales open!
The finishes and furnishings presented on the site are possible specific characteristics of residences, villas and penthouses. The appearance of the materials that will actually be used in the decoration may differ from how they are shown in the images on the site. At the discretion of the developer, finishing materials can be replaced, provided that their class and general stylistic solution are preserved.