8-800-100-51-37
Сonstruction progress
* Сonstruction progress

13.01.2023

Общая готовность резиденций - 79,5%. Фасад - 70,2%. Завершается монтаж кровли. Внутренние инженерные сети - 83,4%. Черновая отделка – 90,3%. Urban villas - 58,2% 5* отель - 68,4%. Конгресс-центр – 66,8%. Начато строительство отдельно стоящего ресторана.

23.12.2022

Overall, the residences are 77.3% ready. The walls and the partitions are 91.3% installed. 67% of the façade has been insulated. The roof installation is being completed. The internal engineering networks are 84.7% complete. The rough finishing is 88.2% complete. The final finishing is underway. The walls, the roofs and the internal communications are being installed in the buildings of the urban villas, rough finishing continues. Overall, the urban villas are 50% ready. The five-star hotel is 66.3% ready. The glazing is 83% complete. The roof is 73.5% complete. The rough finishing continues. The construction of the convention center continues. The building is 65.8% ready.

16.12.2022

Overall, the residences are 77.3% ready. The walls and the partitions are 91.3% installed. 67% of the façade has been insulated. The roof installation is being completed. The internal engineering networks are 84.7% complete. The rough finishing is 88.2% complete. The final finishing is underway. The walls, the roofs and the internal communications are being installed in the buildings of the urban villas, rough finishing continues. Overall, the urban villas are 50% ready. The five-star hotel is 66.3% ready. The glazing is 83% complete. The roof is 73.5% complete. The rough finishing continues. The construction of the convention center continues. The building is 65.8% ready.

09.12.2022

Общая готовность резиденций составляет 77%. Стены и перегородки смонтированы на 91%. Кровля на 98%. Внутренние инженерные сети готовы на 88%. Черновая отделка - 88%. Ведётся чистовая отделка. В зданиях урбан виллас кровля смонтирована на 42%. Инженерные сети на 40%. Пятизвёздочный отель готов на 66%. Остекление выполнено на 83%. Инженерные сети на 69%. Общая готовность конгресс-центра - 65%.

02.12.2022

Мы обеспечиваем высокие темпы строительства MANTERA Seaview residence. Общая готовность зданий резиденций составляет 77%. Стены и перегородки смонтированы на 90%. На 97% готова кровля. Внутренние инженерные сети смонтированы на 84%. Черновая отделка выполнена на 87%. Ведётся чистовая отделка. В зданиях urban villas осуществляется монтаж стен, кровли и внутренних коммуникаций, продолжается черновая отделка. Пятизвёздочный отель готов на – 66%. Остекление выполнено на 83%. Готовность кровли – 73%. Продолжается строительство конгресс-центра. Готовность здания – 65%.

25.11.2022

Overall, the residences are 76.3% ready. The walls and the partitions are 89.4% ready. The facade is insulated by 62.3%. The roof installation is being completed. The internal engineering networks are 84% ready. The rough finishing is 85.6% ready. The final finishing is in progress. The installation of the walls, the roof and internal communications and the rough finishing is underway in the Urban Villas. Overall, the Urban Villas are 48.7% ready. The five-star hotel is 65.3% ready. The glazing is 81% complete. The roof is 73% complete. The construction of the convention center continues. Overall, the building is 64% ready.

18.11.2022

Общая готовность резиденций составляет 75,5%. Стены и перегородки смонтированы на 88%. Фасад утеплён на 60%. Завершается монтаж кровли. Внутренние инженерные сети и черновая отделка готовы на 84%. Ведётся чистовая отделка. В зданиях урбан виллас ведётся монтаж стен, осуществляются устройство кровли и внутренних коммуникаций, организована черновая отделка. Пятизвёздочный отель готов на 65%. Остекление выполнено на 81%. Монтаж кровли завершен на 73%. Продолжается строительство конгресс-центра. Готовность здания – 63%.

04.11.2022

An overview of the deluxe-class MANTERA Seaview residence complex construction progress. Overall, the residence buildings are 75% ready. The walls and the partitions are 87% ready. The internal engineering networks and the rough finishing are 83% ready. The final finishing is 8% ready. Overall, the 5* hotel building is 64% ready. The glazing is 78% ready. The roof is 73% ready. The engineering networks are 64% ready. Overall, the convention center is 61% ready. The roof is 80% ready. The glazing is 100% ready. The installation of the roof and engineering networks of the Urban Villas continues.

28.10.2022

The complex is more than 60% ready. The residence buildings, where the installation of the walls and the partitions, the insulation of the facades, the installation of the engineering networks, rough finishing is underway now, are 74% ready. At the same time, in the urban villa buildings, builders are installing the roof and the internal communications, carrying out rough finishing. In the building of the five-star hotel, the glazing is 78.5% complete. The roof is 73% ready, the engineering systems are 62% ready. The convention center is 60% ready. The partitions, the roof are being installed here, rough finishing is being carried out.

14.10.2022

Общая готовность проекта MANTERA Seaview residence составляет 58,5%. В зданиях резиденций осуществляется внутренняя черновая отделка. Стены и перегородки смонтированы на 77%. Фасад утеплён на 49%. Готовность внутренних инженерных сетей составляет 81%. В зданиях urban villas ведётся монтаж кровли, стен, инженерных сетей. В здании пятизвёздочного отеля продолжается монтаж кровли. Остекление завершено на 77%, монтаж инженерных сетей в здании выполнен на 59%. В конгресс-центре строители монтируют стены и перегородки. Одновременно продолжается работа по устройству уличных бассейнов на территории комплекса. К строительству привлечено более 900 человек и свыше 30 единиц спецтехники.

07.10.2022

Overall, the residences are 73% ready. The roof has been completed. The internal engineering networks in the buildings are 80.5% ready. The rough finish has been completed by 75.8%. The walls have been completed, the installation of the roof and the internal engineering systems has started in the urban villas. The internal walls and partitions are 27.1% ready. Overall, the five-star hotel is 61.6% ready. The glazing has been completed by 76.6%. The roof has been completed by 72.7%. In the building of the convention center, the roof has been completed by 80%. The glazing is 92.1% ready.

22.09.2022

Overall, the residences are 71% ready. The internal engineering networks in the buildings are 78% ready. The roof is 91.5% ready. The rough finish has been completed by 72%. The walls are being laid in the urban villas, these works have been completed by 97%. Overall, the five-star hotel is 61% ready. The glazing has been completed by 75.5%. The roof has been completed by 72%. In the building of the convention center, the roof has been completed by 80%. The glazing is 82% ready.

16.09.2022

Обзор динамики строительства комплекса deluxe-класса MANTERA Seaview residence.Общая готовность резиденций - 70,5%. Внутренние инженерные сети - 76%. Urban Villas: Кладка стен - 97%. Общая готовность пятизвездочного отеля - 60%. Остекление отеля - 75,5%, кровля - 61%. Конгресс-центр: остекление - 82%, кровля - 80%.

01.09.2022

The glazing of the residences has been fully completed. 57% of the masonry walls and partitions have been completed. 54% of the facade has been insulated. The apartment roof is 81% complete. 73% of the engineering networks have been installed. 66% of the rough finish has been completed, and finishing works have already been organised. In the building of the five-star hotel, the glazing is 75% complete. The roof of the hotel is 53% ready, and the engineering networks are 50% ready. At the same time, the construction of the urban villas continues, the installation of the walls and the partitions is underway. 67% of the off-site networks has been installed. More than 800 people and 15 units of equipment are being involved in the construction work.

18.08.2022

Overview of the deluxe-class MANTERA Seaview residence complex construction progress. ◽The residence buildings are 66.5% complete. ◽The urban villas (monolithic structures) are 100% complete. The installation of the walls and the partitions continues. ◽The 5* Hotel. The glazing is 75% complete, the roofing is 52% complete. ◽The convention centre. The glazing is 77% complete, the roofing is 73% complete. ◽The on-site networks are 67% complete.

29.07.2022

The residence buildings are 64.6% ready. The internal engineering networks are 64.7% complete. In the urban villas, the installation of walls and partitions continues. They are 62.4% ready. The 5* hotel building is 55.2% ready. The glazing is 70% complete. The monolithic structures of the convention centre have been completed. The roof is 59% covered. The off-site networks are 66.7% ready. The construction of the outdoor pools continues. 893 people and 15 pieces of equipment are involved.

15.07.2022

The elite MANTERA Seaview residence complex has been constructed at almost cosmic speed. The residence buildings are 63.5% complete. The glazing is complete. The roof is 70% installed. The internal engineering networks are 63% ready. In the buildings of the urban villas, the installation of the monolithic structures has been completed. Builders are assembling walls and partitions. The five-star hotel is 54% ready. The glazing is 68% complete. The roof and the engineering networks are 43% ready. The supporting structures of the convention centre are 99% assembled. The laying of the internal and external networks continues. The construction of 4 outdoor pools is underway.

22.06.2022

The installation of facades and roofs continues in the residence buildings. Glazing in Block A has been fully completed, in Block B it is 99% complete. Glazing in the building of the five-star hotel is 68% complete. The supporting structures of the convention center are 96% assembled. In the urban villas, structural elements are 98% ready. The construction of 5 out of 11 outdoor pools is underway.

15.06.2022

In-situ concrete works have been fully completed in the five-star hotel. Glazing is 65% complete. In the residence buildings, the installation of facades and roofs and internal rough-in continue. Glazing is 99% complete. As for the convention centre, its structural elements are 92% ready. The load-bearing structures of the urban villas frame are 93% assembled. The construction of four outdoor swimming pools continues.

27.05.2022

We ensure the rapid pace of the construction of the deluxe-class MANTERA Seaview residence complex. In the residence buildings, glazing is 83% complete. 48% of the internal engineering systems and networks have been installed. The installation of the facades and roofs of the residences continues. The structural elements of the urban villas are 64% ready. In the five-star hotel building, monolithic work is being completed, glazing is 60% ready. 82% of the framework structures of the conference centre building have been assembled.