12.05.2023
Overall, the residences are 80,5% ready. The walls and the partitions are 89.6% complete. The façade is 60% ready, the internal finishing is 53% complete, the engineering systems are 86.5% complete. The five-star hotel is 74% ready. The construction of the convention center continues. The building is 68.6% ready. The pools are 69,4% complete. The landscaping of the territory of the complex is 27,4% complete.
05.05.2023
Overall, the residences are 80% ready. The walls and the partitions are 89.6% complete. The façade is 60% ready, the internal finishing is 53% complete, the engineering systems are 86.5% complete. The five-star hotel is 73.8% ready. The construction of the convention center continues. The building is 68.6% ready. The pools are 67% complete. The landscaping of the territory of the complex is 26.5% complete
14.04.2023
Overall, the residences are 81% ready. The walls and the partitions are 89,5% complete. The internal residence finishing is 53% complete, the engineering systems are 86,5% complete. The five-star hotel is 73% ready. The convention center is 68% ready. The pools are 62% complete. The landscaping of the territory of the complex continues.
07.04.2023
Общая готовность резиденций составляет 81%. Стены и перегородки смонтированы на 89%. Внутренняя отделка резиденций– 53%, инженерные системы – 86%. Готовность пятизвездочного отеля – 73%. Готовность здания конгресс-центра составляет 68%. Бассейны реализованы на 60%. Продолжается благоустройство территории комплекса.
23.03.2023
Overall, the residence buildings are 80% ready. The walls and the partitions are 89% complete. The internal finishing is 53% complete, the engineering systems are 86% complete. The five-star hotel is 72% ready. The construction of the convention center continues. The building is 67% ready. The pools are 40% complete. The landscaping of the territory of the complex continues.
10.03.2023
Overall, the residence buildings are 80% ready. The walls and the partitions are 89% complete. The roof works have been finished. The internal finishing is 52.6% complete, the engineering systems are 86% complete. The five-star hotel is 71.6% ready. The construction of the convention center continues. The building is 66.8% ready. The pools are 40% complete. The landscaping of the territory of the complex continues.
02.03.2023
Overall, the residence buildings are 80% ready. The engineering networks are 86% complete. The walls and the partitions are 89% complete. Overall, the five-star hotel is 71% ready. The hotel glazing is 95% complete. The roof is 86% complete. The convention center is 67% ready. The roof is 80% ready. The walls and the partitions are 75% complete.
22.02.2023
Let us tell you about the progress of the construction of MANTERA Seaview residence. The residences are 80% ready. The installation of the walls and the engineering systems, façade work, interior decoration is underway. The five-star hotel is 71% ready. The insulation of the façade, the installation of the roof, engineering equipment, interior decoration, and the installation of the walls and the partitions continue. The convention center is 67% ready. Builders are installing the roof, the walls, insulating the façade, and laying engineering networks in the building. Inside, communications are being installed, pools are being arranged. The construction is being carried out by more than 700 people.
09.02.2023
MANTERA Seaview residence is nearing completion. The residence buildings are 80% ready. The engineering networks are 84% ready. The roof is 100% ready. The façade is 68% ready. Overall, the Urban Villas are 67% ready, their engineering networks are 61% ready. Their glazing is 45% ready. The five-star hotel is 69% complete. Its glazing is 90% complete, its roof is 86% complete. The convention center is 67% ready, its engineering networks are 63% ready, its glazing has been completed.
02.02.2023
Overall, the residences are 79.7% ready. 88.7% of the walls and the partitions have been installed. 67.8% of the façade has been insulated. The roof installation is being completed. The internal finishing is 50% complete, the engineering networks are 84.2% complete. The installation of the walls, the roof and the internal communications and the rough finishing continue in the urban villas buildings. Overall, the urban villas are 65.35% ready. The 5* hotel is 68.6% ready. The construction of the convention center continues. The building is 66.8% ready.
13.01.2023
Overall, the residences are 79.5% ready. The façade is 70.2% ready. The roof installation is being completed. The internal engineering networks are 83.4% ready. The rough finishing is 90.3% ready. The urban villas are 58.2% ready. The five-star hotel is 68.4% ready. The convention center is 66.8% ready. The construction of a standalone restaurant has begun.
23.12.2022
Overall, the residences are 77.3% ready. The walls and the partitions are 91.3% installed. 67% of the façade has been insulated. The roof installation is being completed. The internal engineering networks are 84.7% complete. The rough finishing is 88.2% complete. The final finishing is underway. The walls, the roofs and the internal communications are being installed in the buildings of the urban villas, rough finishing continues. Overall, the urban villas are 50% ready. The five-star hotel is 66.3% ready. The glazing is 83% complete. The roof is 73.5% complete. The rough finishing continues. The construction of the convention center continues. The building is 65.8% ready.
16.12.2022
Overall, the residences are 77.3% ready. The walls and the partitions are 91.3% installed. 67% of the façade has been insulated. The roof installation is being completed. The internal engineering networks are 84.7% complete. The rough finishing is 88.2% complete. The final finishing is underway. The walls, the roofs and the internal communications are being installed in the buildings of the urban villas, rough finishing continues. Overall, the urban villas are 50% ready. The five-star hotel is 66.3% ready. The glazing is 83% complete. The roof is 73.5% complete. The rough finishing continues. The construction of the convention center continues. The building is 65.8% ready.
09.12.2022
Overall, the residences are 77% ready. The walls and the partitions are 91% installed. The roof is 98% ready. The internal engineering networks are 88% ready. The rough finishing is 88% complete. The final finishing is underway. In the urban villa buildings, 42% of the roof has been installed. The engineering networks are 40% ready. The five-star hotel is 66% ready. The glazing is 83% complete. The engineering networks are 69% ready. Overall, the convention center is 65% ready.
02.12.2022
We're ensuring the high rates of the construction of MANTERA Seaview residence. Overall, the residence buildings are 77% ready. The walls and the partitions are 90% installed. The roof is 97% complete. The internal engineering networks are 84% installed. The rough finishing is 87% complete. The final finishing is underway. The walls, the roofs and the internal communications are being installed in the buildings of the urban villas, rough finishing continues. The five-star hotel is 66% ready. The glazing is 83% completed. The roof is 73% ready. The construction of the convention center continues. The building is 65% ready.
25.11.2022
Overall, the residences are 76.3% ready. The walls and the partitions are 89.4% ready. The facade is insulated by 62.3%. The roof installation is being completed. The internal engineering networks are 84% ready. The rough finishing is 85.6% ready. The final finishing is in progress. The installation of the walls, the roof and internal communications and the rough finishing is underway in the Urban Villas. Overall, the Urban Villas are 48.7% ready. The five-star hotel is 65.3% ready. The glazing is 81% complete. The roof is 73% complete. The construction of the convention center continues. Overall, the building is 64% ready.
18.11.2022
Общая готовность резиденций составляет 75,5%. Стены и перегородки смонтированы на 88%. Фасад утеплён на 60%. Завершается монтаж кровли. Внутренние инженерные сети и черновая отделка готовы на 84%. Ведётся чистовая отделка. В зданиях урбан виллас ведётся монтаж стен, осуществляются устройство кровли и внутренних коммуникаций, организована черновая отделка. Пятизвёздочный отель готов на 65%. Остекление выполнено на 81%. Монтаж кровли завершен на 73%. Продолжается строительство конгресс-центра. Готовность здания – 63%.
04.11.2022
An overview of the deluxe-class MANTERA Seaview residence complex construction progress. Overall, the residence buildings are 75% ready. The walls and the partitions are 87% ready. The internal engineering networks and the rough finishing are 83% ready. The final finishing is 8% ready. Overall, the 5* hotel building is 64% ready. The glazing is 78% ready. The roof is 73% ready. The engineering networks are 64% ready. Overall, the convention center is 61% ready. The roof is 80% ready. The glazing is 100% ready. The installation of the roof and engineering networks of the Urban Villas continues.
28.10.2022
The complex is more than 60% ready. The residence buildings, where the installation of the walls and the partitions, the insulation of the facades, the installation of the engineering networks, rough finishing is underway now, are 74% ready. At the same time, in the urban villa buildings, builders are installing the roof and the internal communications, carrying out rough finishing. In the building of the five-star hotel, the glazing is 78.5% complete. The roof is 73% ready, the engineering systems are 62% ready. The convention center is 60% ready. The partitions, the roof are being installed here, rough finishing is being carried out.
14.10.2022
Общая готовность проекта MANTERA Seaview residence составляет 58,5%. В зданиях резиденций осуществляется внутренняя черновая отделка. Стены и перегородки смонтированы на 77%. Фасад утеплён на 49%. Готовность внутренних инженерных сетей составляет 81%. В зданиях urban villas ведётся монтаж кровли, стен, инженерных сетей. В здании пятизвёздочного отеля продолжается монтаж кровли. Остекление завершено на 77%, монтаж инженерных сетей в здании выполнен на 59%. В конгресс-центре строители монтируют стены и перегородки. Одновременно продолжается работа по устройству уличных бассейнов на территории комплекса. К строительству привлечено более 900 человек и свыше 30 единиц спецтехники.
We will pick a residence for you and prepare a calculation of its profit potential. please leave your contact details for a personal offer.
Soon the start of sales of a new pool of residences.
Leave a request, we will add you to the waiting list.
Find out more about the types of residences, convertible floor plans and current prices.
The cost of residences from 175 million rubles
SOLD OUT*
We are pleased to put you on the waiting list for another FIVE project.
Soon the start of sales of a new pool of residences.
Leave a request, we will add you to the waiting list.
Welcome toMantera Seaview residence! Be the first to book the best option when the sales open!
The finishes and furnishings presented on the site are possible specific characteristics of residences, villas and penthouses. The appearance of the materials that will actually be used in the decoration may differ from how they are shown in the images on the site. At the discretion of the developer, finishing materials can be replaced, provided that their class and general stylistic solution are preserved.