8-800-100-51-37
Сonstruction progress
* Сonstruction progress

16.09.2022

Обзор динамики строительства комплекса deluxe-класса MANTERA Seaview residence.Общая готовность резиденций - 70,5%. Внутренние инженерные сети - 76%. Urban Villas: Кладка стен - 97%. Общая готовность пятизвездочного отеля - 60%. Остекление отеля - 75,5%, кровля - 61%. Конгресс-центр: остекление - 82%, кровля - 80%.

01.09.2022

The glazing of the residences has been fully completed. 57% of the masonry walls and partitions have been completed. 54% of the facade has been insulated. The apartment roof is 81% complete. 73% of the engineering networks have been installed. 66% of the rough finish has been completed, and finishing works have already been organised. In the building of the five-star hotel, the glazing is 75% complete. The roof of the hotel is 53% ready, and the engineering networks are 50% ready. At the same time, the construction of the urban villas continues, the installation of the walls and the partitions is underway. 67% of the off-site networks has been installed. More than 800 people and 15 units of equipment are being involved in the construction work.

18.08.2022

Overview of the deluxe-class MANTERA Seaview residence complex construction progress. ◽The residence buildings are 66.5% complete. ◽The urban villas (monolithic structures) are 100% complete. The installation of the walls and the partitions continues. ◽The 5* Hotel. The glazing is 75% complete, the roofing is 52% complete. ◽The convention centre. The glazing is 77% complete, the roofing is 73% complete. ◽The on-site networks are 67% complete.

29.07.2022

The residence buildings are 64.6% ready. The internal engineering networks are 64.7% complete. In the urban villas, the installation of walls and partitions continues. They are 62.4% ready. The 5* hotel building is 55.2% ready. The glazing is 70% complete. The monolithic structures of the convention centre have been completed. The roof is 59% covered. The off-site networks are 66.7% ready. The construction of the outdoor pools continues. 893 people and 15 pieces of equipment are involved.

15.07.2022

The elite MANTERA Seaview residence complex has been constructed at almost cosmic speed. The residence buildings are 63.5% complete. The glazing is complete. The roof is 70% installed. The internal engineering networks are 63% ready. In the buildings of the urban villas, the installation of the monolithic structures has been completed. Builders are assembling walls and partitions. The five-star hotel is 54% ready. The glazing is 68% complete. The roof and the engineering networks are 43% ready. The supporting structures of the convention centre are 99% assembled. The laying of the internal and external networks continues. The construction of 4 outdoor pools is underway.

22.06.2022

The installation of facades and roofs continues in the residence buildings. Glazing in Block A has been fully completed, in Block B it is 99% complete. Glazing in the building of the five-star hotel is 68% complete. The supporting structures of the convention center are 96% assembled. In the urban villas, structural elements are 98% ready. The construction of 5 out of 11 outdoor pools is underway.

15.06.2022

In-situ concrete works have been fully completed in the five-star hotel. Glazing is 65% complete. In the residence buildings, the installation of facades and roofs and internal rough-in continue. Glazing is 99% complete. As for the convention centre, its structural elements are 92% ready. The load-bearing structures of the urban villas frame are 93% assembled. The construction of four outdoor swimming pools continues.

27.05.2022

We ensure the rapid pace of the construction of the deluxe-class MANTERA Seaview residence complex. In the residence buildings, glazing is 83% complete. 48% of the internal engineering systems and networks have been installed. The installation of the facades and roofs of the residences continues. The structural elements of the urban villas are 64% ready. In the five-star hotel building, monolithic work is being completed, glazing is 60% ready. 82% of the framework structures of the conference centre building have been assembled.

20.05.2022

The rapid pace of construction is being kept at MANTERA Seaview residence. In the residence buildings, glazing is 79% complete. Internal rough-in continues, builders are insulating the facades, assembling the roof. The urban villas are being actively built - the structural elements are 54% ready. The installation of the monolithic structures of the five-star hotel is at the final stage - 98% ready, glazing is 60% complete. The conference centre building is under construction. The load-bearing structures are 70% ready. 67% of the off-site networks have been installed.

22.04.2022

Builders have started installing the on-site water supply and sanitation networks. In the residence buildings, the facades continue to be insulated, and the roof is being installed. Glazing in the residence buildings is 62% complete. In blocks A and B, internal rough-in has begun in sections A1 and B1. In the five-star hotel building, glazing and the installation of the internal engineering systems continue. Monolithic work here is 96% complete, glazing is 47% ready. The construction of the urban villas has reached the level of the second floor. At present, the installation of the monolithic structures of the first and second floors of the building is underway. The load-bearing structures of the frame of the conference centre building are also being installed.

15.04.2022

On the territory of the MANTERA Seaview residence project, the laying of a structured cabling system was organised as part of the construction and installation works. The communication cables will ensure the operation of the networks and equipment responsible, among other things, for security and video surveillance. At the same time, builders continue to insulate facades, install roofs, lay internal engineering systems, and glaze windows in the residence buildings. Also, the construction of the urban villas is already at the level of the 2nd floor. Monolithic works are being completed in the five-star hotel. The conference centre is being set up.

08.04.2022

Several parts of the complex are being constructed at once. In the residence buildings, the roofs and the internal engineering systems are being installed, glazing is being carried out, and the facade is being insulated. The construction of the urban villas continues, work is being performed at the level of the first floors. Monolithic works are being completed in the five-star hotel building. On the first floor, a swimming pool bowl is being formed. Glazing is in progress. The internal communications have been installed. The supply lines have been completed.

22.03.2022

MANTERA Seaview residence shows a stable construction pace. After monolithic work and laying of walls and partitions were completed in the residence buildings, the main front of tasks shifted to glazing and insulation of the facades. Simultaneously with glazing, the installation of the facade subsystem and the plaster layer, the installation of the roof is now being carried out, the installation of the internal water supply, ventilation, heat supply, sewerage, air conditioning and power supply systems is underway. The urban villas are being actively built. In block B, monolithic works are carried out at the level of the first floor. In the five-star hotel, monolithic work is 90% complete. Masonry is 68% complete. Glazing and the insulation of the facades is underway. The construction of the metal frame of the conference centre is underway. The laying of external sewerage and water supply networks has been completed, cable networks have been installed.

16.03.2022

At the moment, the complex is in the stage of significant construction completeness. Monolithic works in the residence buildings have been completed. Roofing is in progress. The installation of internal engineering systems is underway. The builders have begun interior finishing work. The structural elements of the first floor of the urban villas, an exclusive format in the deluxe segment of the real estate market, are being installed.The construction of the five-star hotel is at the final stage. Glazing is underway, the builders are installing internal engineering networks and insulating the facade. The metal structures of the convention center are also being installed.

04.03.2022

The MANTERA Seaview residence deluxe-class complex is getting closer and closer to its final look. The laying of walls and partitions of eight-storey residences has been completed. The installation of the roof, as well as the glazing of windows, has begun. Section A1 of block A is fully glazed, except for the first floors and windows located in the hallways. In the block of section A2, 5% of glazing has been completed. Section B1 of block B is 70% glazed. At the same time, work began on the installation of the internal engineering systems of the five-star hotel. Glazing of windows on the 2nd and 3rd floors, 4th floors is 50% complete. The installation of metal structures for the frame of the convention center building continues. The foundations and walls of the first floors of urban villas are also being constructed.

24.02.2022

The pace of the construction of the MANTERA Seaview residence deluxe-class complex is impressive! Walls and partitions are being completed in the eight-storey buildings of the residences; the installation of windows and stained-glass windows, facades, engineering systems and floor screeds is underway. At the same time, the laying of walls and partitions, the installation of windows, stained-glass windows and facades of the five-star hotel continues. The metal structures of the frame of the convention center building are being erected. Builders have also started laying the foundation of two-storey urban villas. 753 people and over 20 pieces of equipment are working on the construction site.

19.01.2022

The construction of the elite MANTERA Seaview residence complex has reached a new level. Foundation pits were arranged for the facilities of the second phase of the large-scale project - two-storey urban villas, which are an ultra-modern type of real estate of the deluxe-class segment of the Russian market. The 5-7 floors of the five-star hotel and the foundation of the convention center are being built at the same time. In the buildings of the residences, which occupy the main part of the complex, monolithic work has been fully completed, the builders are installing walls and partitions, window structures and internal engineering systems, the facade insulation continues. The high pace of the construction is ensured by the involvement of more than 800 people and more than 30 pieces of special equipment.

24.11.2021

The pace of the construction of the MANTERA Seaview residence deluxe-class complex remains at a stable high level. Builders are constructing the 7th floor of the residences, as well as the 3rd and 4th floors of the five-star hotel. In each building, laying of walls and partitions is organised. A 2.4 km long cable line, through which electricity will be supplied to all facilities of the complex, is being installed at the same time. The readiness of the facilities is ensured by more than 30 pieces of special equipment and over 700 builders.

13.10.2021

The pace of the construction of the MANTERA Seaview residence deluxe-class complex shows a steady growth. The high readiness of the facilities is ensured by enhanced production capabilities. More than 700 people and more than 30 pieces of special equipment are involved in the construction and installation work. The builders are assembling the walls of the fourth and fifth floors of the buildings of the residences, while vertical structures on the third floor of the five-star hotel are being installed. MANTERA Seaview residence is a complex with residences, standing on a par with world benchmarks in the field of the luxury real estate of Miami, Dubai, Spain, USA.

15.09.2021

The elite MANTERA Seaview residence complex rises higher and higher above the central promenade of the Imeretinskaya Bay, elevating the Sirius Federal Territory in Greater Sochi with its majestic view. In September, work on the construction of the walls of the fourth floor of the premium-class residences continues at the construction site. At the same time, the walls of the third floor of the five-star hotel, which will be managed by an international brand, are being installed. With each passing day, all this splendour is turning into an unforgettable place for a luxurious life, symbolising the birth of a completely new type of luxury real estate on the Black Sea coast of Russia.